Wehrhahnlinie & Kaufhof an der Kö, Düsseldorf | Germany

Construction Method: railway stations/ single-sided walls, cut and cover method

 

Company: Bilfinger Construction GmbH, ARGE UKK: Max Bögl Bauunternehmung GmbH & Co.KG / Wayss & Freytag Ingenieurbau AG  

 

Year: 2011 – 2014

 

Description:

On the construction site "Wehrhahn line" in Düsseldorf, MOOSER formwork vibrators® were used for the concrete compaction at almost all stations of the subway. All outer walls to the diaphragm walls in the stations and the outer walls in the barrier floors were successfully compacted by help of the compressed air vibrators from MOOSER.

 


Subsequently MOOSER vibrators® were also used for the outer walls of the access well of the "Kaufhof an der Kö" underpass (a construction in mined technique)